Why know the concrete cost for a construction project?
RH Business Marketing Solutions
There are several reasons for knowing the concrete cost of a construction project. The main thing here is the budgeting cost of the construction project. Concrete does involve key ingredients like gravel, cement, and sand. You can say it is a bottleneck to control the cost of the concrete during the construction project. Concrete is one of the key elements in construction and the Concrete Calculator provides information regarding its quantity.
The quantity and quantity of the concrete is going to change for a project in various spots. Being a construction manager it is necessary to know the ratio of sand, cement, and gravel is not consistent. In the various spots, the ratio of the concrete is going to be changed. You can also reduce the wastage level of the concrete while using the online tool to know a certain quantity of concrete.
Why know the concrete cost?
Concrete is one of the crucial elements for managing the project effectively. It is necessary to manage concrete costs for managing budget, and overall risk management in the project. It is necessary to make well-informed decisions while going through the various stages of the construction project.
· Concrete is a major cost in the overall project cost of the construction project
For resource allocation
Resource allocation is one of the key elements in project management. Being a manager you need to assess how much budget is required to complete a project. Reducing allocation is necessary to divide the resources and manage the cost of each step of the project.
· Maintaining a check on the cost of concrete also assists in allocating resources and finance to other projects.
Risk management
Risk management is another thing in the construction projects. There can be changing processes of the material due to uncertain economic conditions. The cost of the project may be increased due to inflation. If a manager already managed the cost of concrete with the concrete calculator. Then it is easy to manage costs for other construction materials.
· Manage risk and overall cost of the project by managing the cost of the concrete.
On-time completion
Just in time completion is necessary for project management. The concrete cost varies in the market so it is quite helpful to manage the project cost. The concrete radius calculator provides a simple solution for the project manager to manage the cost of concrete.
How to Calculate Concrete Cost?
Let's consider a construction Mangere needs 1000 circular concrete slabs. The diameter of each slab is 2 ft and the depth of each slab is 5 inches. Calculate the quantity of concrete required for 1000 circular concrete slabs. Suppose the cost of each slab is dollar $ 2
Given:
Number of circular tiles = 100slabs
Diameter of Slab = 2 ft
Depth of Slab = 5 inches
Depth of Slab = 5/12 = 0.42 feet
Required Concrete =?
Solution:
Now
Diameter of circular Slab = 2 ft
Then
Radius = 2/2= 1 ft
Area(ft^2) = 3.14[Diameter/2]^2
Area(ft^2) = 3.14[Radius]^2
Area(ft^2) = 3.14[1]^2
Area(ft^2) = 3.14 ft^2
Quantity of concrete(ft^3) = (Depth)(Area)
Quantity of concrete(ft^3) = (0.42 )(3.14)
Quantity of concrete(ft^3) = 1.3188 ft^3
Concrete for rounded slab = 1.3188 ft^3
Required Concrete for 1000 slabs = (1.3188 ft^3)(1000)
Required Concrete for 1000 slabs = 1,318.8 ft^3
cost of circular slabs for 1000 slabs= ($ 2)(1,318.8)
cost of circular slabs for 1000 slabs= $ 2638
The calculator for concrete cost and volume provides a simple solution to the construction manager.
Conclusion
Construction managers do need to understand the cost of the project can vary for different projects. The quantity of the concrete is going to vary for different places. For example in roofs, you need altogether a different ratio of concrete compared to the flooring of the project. Most of the time square footage of concrete is different due to the varying requirements of the construction site.